HUDSON CORRECTIONAL FACILITY: PROGRESS
| Hudson Aerial Progress Photos |
Date and Description |
 |
August 8, 2008
Located in the west half of section 26 in the Town of Hudson, County of Weld this approximately 50 acre piece of land is being excavated for the site of the new Hudson Correctional Facility. |
 |
August 25, 2008
Aerial photo of the future home of the new Hudson Correctional Facility, a 1,250 bed medium security facility. With an expected 16 month construction period, the facility is expected to be completed in November of 2009. |
|
September 25, 2008
Progressing as expected, this facility is inspected up to twice a month and funding is done through draw requests that are approved via Owners Representatives. |
|
October 27, 2008
Aerial photo of the construction stage, seen here the frame work of three buildings are started. |
|
November 30, 2008
Aerial photo of the future home of the new Hudson Correctional Facility, a 1,250 bed medium security facility. With an expected 16 month construction period, the facility is expected to be completed in November of 2009. |
|
December 31, 2008
Aerial photo of the Hudson Correctional Facility. When completed the site will contain a total of eight buildings with four housing units for incarceration, one administration building, one support services building, one gate house for visitors, attorneys, and employees, and one warehouse building. |
|
January 17, 2009
Included in the development plan was new capacity for a deep fresh water well, plus a new waste water treatment facility to supplement the municipality’s current capacity were also a part of the overall transaction. |
|
February 25, 2009
Here you can see the four buildings that will hold over 300 two man cells each. The long building to the left is the start of the Inmate Services Building and the Administrative Support Building. |
|
March 31, 2009
Here you see the framework of the Inmate Services Building and the Administrative Support Building near completion. |
|
April 23, 2009
With just over six months before the opening of the Facility, construction is going according to plan. |
|
May 20, 2009
The blue roof building is the indoor recreational building, surrounding it to the right will be the soccer/track field. Left is the baseball field and vocational garden. In front will be a shaded structure and a handball court. |
|
June 20, 2009
Cornell announced that they will be looking to hire for 250 positions for November when the prison opens. |
|
July 31, 2009
With construction almost complete, the facility is on schedule to receive inmates in November. |
|